$30.0B — $30B senior notes across six tranches (2030-2065, coupons 4.200%-5.750%), priced Oct 30 2025, closed Nov 3 2025
$30.0B — $30B senior notes across six tranches (2030-2065, coupons 4.200%-5.750%), priced Oct 30 2025, closed Nov 3 2025
Sourced figures 1
- Meta Platforms, Inc. SEC free-writing prospectus (FWP) $30B senior notes, six tranches 2030-2065, joint book-running managers Citigroup Global Markets Inc. and Morgan Stanley & Co. LLC
the working
Basis
$30.0B — $30B senior notes across six tranches (2030-2065, coupons 4.200%-5.750%), priced Oct 30 2025, closed Nov 3 2025
Hypothesized recipients 6
- Meta (datacenter construction (Hyperion campus, Richland Parish LA — JV recipient side, distinct from meta/datacenter-operation's grid-interconnection edge)) → Turner Construction Company (EPC/general-contractor services (seller side))hypothesis
General contractor (scope: the four primary AI data center buildings) at Meta's Hyperion campus, Richland Parish, Louisiana.
- Meta (datacenter construction (Hyperion campus, Richland Parish LA — JV recipient side, distinct from meta/datacenter-operation's grid-interconnection edge)) → DPR Constructionhypothesis
Named general contractor at Meta's Hyperion campus, Richland Parish, Louisiana.
- Meta (datacenter construction (Hyperion campus, Richland Parish LA — JV recipient side, distinct from meta/datacenter-operation's grid-interconnection edge)) → Entergy Louisiana (power generation buildout)hypothesis
$11.0B (estimate) — Entergy Louisiana is building 10 gas-fired power plants (7+ GW total, expanded from an initial 3-plant ~2,260MW plan) to power Hyperion; Meta funds the full 15-year revenue requirement. Estimated systemwide cost of the 10 plants: approximately $11B -- an estimate, not a confirmed invoice. Turbine OEM (GE Vernova/Siemens Energy/Mitsubishi Power) not publicly confirmed.
- Meta (datacenter construction (Hyperion campus, Richland Parish LA — JV recipient side, distinct from meta/datacenter-operation's grid-interconnection edge)) → Louisiana local vendors (Meta Hyperion contractors)hypothesis
$875.0M — Meta states it has contracted more than $875M with roughly 160 Louisiana vendors (84% local to Northeast Louisiana) for the Hyperion campus, including named subcontractors Copeland Electric Co. (electrical) and 1LEMOINE (paving/utilities) -- an aggregate figure, not itemized per vendor.
- Meta (datacenter construction (Hyperion campus, Richland Parish LA — JV recipient side, distinct from meta/datacenter-operation's grid-interconnection edge)) → Mortenson Constructionhypothesis
Named general contractor at Meta's Hyperion campus, Richland Parish, Louisiana.
- Meta (datacenter construction (Hyperion campus, Richland Parish LA — JV recipient side, distinct from meta/datacenter-operation's grid-interconnection edge)) → Williams Companies (Will-Power subsidiary)hypothesis
Williams' Will-Power subsidiary is building a ~200MW gas-fired 'Socrates South' plant to power Meta's New Albany, Ohio ('Prometheus') data center; no dollar figure disclosed.
A claim is one metric we assert about a node — the value is the summary, this page is the receipt. Sourced from kestrel; supersedes-history not yet shown. Back to Meta.