The nuclear-for-AI wave — but ~0 net-new MW power any AI datacenter before 2027, and the first firm power is a RESTART (TMI-1), not a new build. The ~13GW announced is <20% of projected demand; every genuinely new SMR/Gen-IV project is 2030s-weighted. Watch which actually clear licensing.